Buying a home that does not exist yet is scarier than buying a finished one, and the fear has legitimate reasons. Nearly all of them are settled by reading three contract clauses and putting two inspections on the calendar.

Updated 11/11/2026

Quick answer

A builder home in Central Florida takes 5 to 9 months from signing to handover. The reservation deposit runs from 5,000 to 10,000 dollars and the rest is paid at closing, not during construction. The delivery date in the contract is an estimate: know from the start what happens if it slips and how late you can change selections without a charge.

The first reassurance: you are not financing the build

In many countries, buying off plan means paying installments during construction. That is not how it works here with the large builders. You pay the reservation deposit at signing and the entire balance on closing day, when the home is finished and has its certificate of occupancy.

That changes the risk completely: your money is not sitting inside an unfinished building. If you finance, the loan also closes at the end, with the home complete, and it is an ordinary mortgage, not a construction loan.

The three clauses to read before signing

The delivery date and what happens if it slips

The contract date is an estimate, not a promise. What matters is the language defining how much delay is acceptable, what rights you have past that point, and whether the deposit is returned. I ask for that paragraph flagged and translated before any signature.

What happens if the rate changes

If you finance, the builder's rate incentive usually has an expiration date. On an eight-month build that matters a great deal. You need to know whether the rate can be locked and for how long, and what happens if it expires before closing.

The cutoff for selections and changes

There is a date, fairly early on, after which nothing can be changed without a charge. Past that date, swapping a countertop stops being a decision and becomes a change order with a price.

The real schedule, stage by stage

StageTypical durationWhat to do
Permits and lot preparation4 to 8 weeksconfirm lot, orientation and neighbors
Foundation and slab2 to 3 weeksphotos before the pour
Framing and roof4 to 6 weeksdry-in visit, before walls close
Systems before drywall3 to 4 weeksprivate pre-drywall inspection
Interior finishes6 to 10 weeksreview the selections you chose
Certificate of occupancy and closing2 to 3 weeksfinal walkthrough with punch list

Typical timelines observed in the Orlando area communities during 2026. Weather, county permitting and material availability move them. The builder updates the schedule during construction and I pass it on to you with photos.

The two inspections worth every penny

The builder runs its own inspections and the county runs the official ones. Even so, I recommend hiring a private inspector twice. It costs a few hundred dollars and it is the best insurance in the process.

If you are outside the country, I do the walkthroughs live on video and the private inspector sends the report with photos. It is what most of my clients abroad do.

Selections: where the budget leaks without you noticing

The model home is built to make you fall in love and is almost never what comes included. The display finishes are usually paid upgrades. My practical advice, after seeing many homes delivered, is simple.

The warranty, in plain terms

Every builder has its own document, so I always ask for it in writing before the reservation. The general shape has three layers: a short period for finishes and cosmetic items, an intermediate period for electrical, plumbing and HVAC systems, and a long period for structural elements.

Two pieces of advice that save arguments: note any defect the moment you see it and report it in writing, even if it seems minor, because cosmetic windows are short. And keep everything in one folder: contract, warranty, inspection reports, change orders and the signed final walkthrough.

General information about buying new construction in Central Florida. Not legal advice: terms, timelines and warranties are set by each builder's contract, which I always review with you before signing.

Frequently asked questions

What I get asked most

How long does a new home take to build in Florida?
Between 5 and 9 months from contract signing to handover, depending on the floor plan, county permitting and weather. If you need to move sooner, there is finished inventory that closes in 30 to 60 days.
Do I pay installments during construction?
No. You pay the reservation deposit at signing and the full balance on closing day, once the home has its certificate of occupancy. If you finance, the loan also closes at the end.
What happens if construction is delayed?
The contract date is an estimate, and the contract itself defines the acceptable margin of delay and your rights if it is exceeded. It is one of the clauses I review with you line by line before signing.
Is a private inspector worth it on a brand new home?
Yes, especially at the pre-drywall stage, when the systems are exposed. It costs a few hundred dollars and it is the only chance to see what ends up inside the walls.
Can I buy under construction from outside the country?
Yes. I do live video walkthroughs at each stage, the private inspector sends reports with photos, and closing can be signed remotely or through a power of attorney.